Refine by

const. Of Level Ii Water System

Project Year
Program
Project ID
Implementing Agency
Project Type
Allocated Budget
Project Status
2014
POTABLE WATER
19
DILG
WATER & SANITATION
₱3,040,000
completed

const. Of Level Ii Water System
Date Updated Feb 10, 2017

  • Implementation by: LGU
  • LGU Counterpart Funding: ₱0
  • Final Project Amount: ₱3,040,000

Location: BUCAY, ABRA, CAR

Financial Disbursement
2014 Q4                    ₱0
2016 Q3                    ₱1,520,000
2016 Q4                    ₱1,520,000

Physical Progress